COMMISSION AGENDA
Tay Yoshitani, Chief Executive Officer
February 5, 2009
Page 2 of 6
Port truck and other traffic, improving access to the North SIG Yard and the freeway system
over current conditions.
The Port has received a proposal for the purchase of necessary property and/or property rights at
Terminal 46. The property needed for the project is shown on the attached drawing, with the
land in fee requirement shown in red, and temporary construction easements in the terminal lease
are in other colors. Based on the appraisal prepared for WSDOT, the purchase offer is
$6,566,299. This offer consists of $5,922,840 for 87,582 square feet of land in fee, $767,129 for
94,358 square feet of temporary construction easements, $13,550 for the contributory value of
asphalt paving and chain-link fence improvements, $20,000 for parking lot reconfiguration and
re-striping damages, and a deduction for special benefits in the amount of $157,350. The Port
has hired an appraiser to complete an independent appraisal. This appraisal is not completed;
therefore the Port cannot provide the State with their opinion of fair market value, or to complete
the financial transaction. Initial analysis indicates that there will be some minor adjustments to
the proposed compensation.
Under normal conditions, WSDOT would acquire property and property rights under a Purchase
and Sale Agreement or through Condemnation prior to the actual bid advertisement for the
project work. However WSDOT currently has a late February, 2009 bid advertisement date for
the construction of Phase I of the S. Holgate Street to S. King Street portion of the Alaska Way
Viaduct project. Without Port and TTI approval by February 10, 2009 the WSDOT project
could be delayed with the potential for incurring additional costs and risks.
In order to proceed with the project, WSDOT has proposed a Possession and Use agreement for
the property and property rights they wish to acquire. A Possession and Use Agreement would
allow WSDOT possession and use of the property without the Port having to relinquish the
underlying property rights and without TTI having to relinquish its underlying leasehold rights.
This approach enables the Port and TTI to carry out their own appraisals of the required land in
fee, temporary easements, and other contract components and to negotiate appropriate
compensation. At the same time, WSDOT can proceed with the project. Port staff and TTI staff
have worked with WSDOT on the planning of this project and support this approach.
Subject to Port Commission approval, Port staff and TTI staff have reached agreement under the
Possession and Use Agreement on the allocation of the WSDOT offer. The Port would receive
all of the value for the fee acquisition by WSDOT and TTI has agreed to waive any rights to
such compensation. The Port/TTI lease will be amended to reflect a reduction in the leased area
with a corresponding reduction in rent. TTI would receive the value for the Temporary
Construction Easements as TTI is in possession of the premises. TTI would not be entitled to
rent abatement under the Port/TTI lease for the temporary construction easement areas. WSDOT
will pay the Port as outlined above on July 31, 2009, subject to the final determination of value
for the fee acquisition area.