COMMISSION STAFF BRIEFING
ATTACHMENT A
Terminal 30 Container Terminal Project Status
Terminal 30 major construction is 68% complete. Construction on Phase 2 commenced in mid-
October and is progressing on schedule and on budget. The contractor has notified the Port of
schedule impacts due to severe weather between 12/18/08 and12/30/08, as well as, impacts
associated with investigation of an unknown substance discovered during dredging between
1/2/09 thru 1/6/09.
Concrete pile driving is complete. The north end substation is nearly complete. Concrete work
for truck scales is in progress. Storm drain installation at the reefer rack and equipment slab is
complete, and storm drain work under cruise building is in progress. The Longshore building re-
model is in progress and form work below the deck at waterside crane beam is complete.
Terminal 30 Upland Dredge Disposal Update
Both dredging for upland and open water disposal has commenced as of December 1, 2008. The
dredging operation was delayed due to the snowstorm. It is expected to be completed prior to
February 15, 2009.
Terminal 91 Cruise Terminal Project Status
As of the end of December, Terminal 91 cruise terminal building construction is approximately
90% complete. Drywall installation is nearly complete with much of the second level walls
painted. Significant portion of the second level concrete floor has the final finish sealant applied.
Start-up of air handling units and HVAC system continues. Permanent light fixtures are mostly
in place and trim work underway. Plumbing fixtures are being installed throughout the building.
Escalator and elevator commissioning process continues. Balcony topping slabs are in place.
Seattle City Light shore power agreement is being finalized. Coordination continues with City
of Seattle on city street sign fabrication and installation. The cruise building and terminal yard
sign contract advertised and the bid opening is scheduled for January 14th.
Terminal 30 Project Schedule
The project was impacted by severe weather and unforeseen conditions and the contractor is in
the process of evaluating impacts and necessary recovery plans. Currently, the Beneficial
Occupancy date for the T30 Container Terminal remains May 1, 2009.
Terminal 91 Project Schedule
The building contractor is projecting beneficial occupancy of the cruise terminal building on
February 18, 2009 with temporary certificate of occupancy occurring a couple of weeks earlier if