
ATTACHMENT A
TODAY’S BRIEFING FOR January 27, 2009
Upcoming Commission Actions
Request Commission approval for the following:
Bus Maintenance Facility CNG Design Additional Funding – February 10, 2009
RCF Acquisitions (Cemetery) – April, 2009
RCF Property Acquisitions (WSDOT) – April, 2009
Bus Maintenance Facility Construction – Suspended
Off-Site Roadway Improvements Construction – Suspended
Developments Since Last Update:
Main Contract:
Turner shut down all work from December 18, 2008 through January 7, 2009
Construction suspended except for all necessary work to close the site for up to one year
Dewatered flooded excavations and treated a significant amount of Stormwater without issue
Continuing construction of only those building footings and columns formed with reinforcing
steel set in Area B
Continuing construction only on retaining walls that could become unstable or that will likely
be damaged by sitting through the suspension.
Continuing construction to complete the Detention Vault and get the Building Permit signed
off
Continuing installation of only those underground utilities that support the site shutdown or
that could be damaged or impacted during the suspension
Conducted site walks and determined critical work needed to suspend site construction for up
to one year
Turner reduced staff to eleven, laying off seven employees January 9
th
and reassigned others
to active Turner projects
Continuing review of conforming change orders for each subcontractor
Design:
Completed review of 60% design of the Bus Maintenance Facility and working on 90%
90% design of the Off-Site Road Improvements estimated to be complete in January 2009
Signed contract for the Consultant providing replacement Project Management staff
Continuing to analyze additional after-the-fact design services claims
Issued 10 Design Change Notices to date, four of which were issued after the last
Commission update.
Continuing to review Contractor submittals and request for information (RFI) that were
submitted before the authorization to suspend construction.
Industry:
Technical and Industry meetings held January 14 to discuss an update on Bus Maintenance
Facility project, specifically the CNG station addition
Industry updated on current status and on going work
Advantage has pulled out of the Seattle rental car market.
Item No.: 6a_attach
Date of Meeting: January 27, 2009